This study addresses schedule overruns in offshore oil and gas EPCI projects
caused by the reactive limitations of conventional Critical Path Method (CPM)
networks and S-curve tracking. By analyzing historical execution data from the
Area B Extension Project, the research identifies key Early Warning Indicators
(EWIs), specifically engineering review backlogs and unverified fabrication
progress. To resolve these bottlenecks, a hybrid framework is developed by
embedding micro level Agile tools, including two week sprints, visual Kanban
boards with Work in Progress (WIP) limits, and cross functional Adaptive Action
Plans, directly into macro level CPM schedule governance. Theoretical validation
across near critical 3D modeling and zero float critical path process deliverables
shows that the framework detects emerging delays up to 33 days earlier, preserves
schedule float, eliminates the risks of downstream teams working on unapproved
data, and prevents reactive project rebaselining.