PENGEMBANGAN PRIORITAS DAN STRATEGI PROGRAM PEMELIHARAAN UNTUK SISTEM PIPA PENYALUR MINYAK DAN GAS DENGAN MERAPKAN KAJIAN RESIKO

DEVELOPMENT OF MAINTENANCE PROGRAM PRIORITIZATION AND STRATEGY FOR CRUDE AND GAS PIPELINE SYSTEM BY APPLYING RISK ASSESSMENT

Maret 2018
Master Theses from JBPTITBPP / 2018-03-15 15:21:06
Oleh : Heri Iswanto / 29115240, S2 - MBA-ITB (heri.iswanto@sbm-itb.ac.id)
Dibuat : 2018-03-15, dengan 1 file

Keyword : Pipeline integrity, risk assessment, pipeline maintenance program
Subjek : Business Strategy
Kepala Subjek : Business Strategy
Nomor Panggil (DDC) : 650
Sumber pengambilan dokumen : PT. Chevron Pacific Indonesia

Pipa penyalur minyak dan distribusi gas merupakan salah satu fasilitas pendukung utama operasi produksi yang dilakukan oleh PT. Chevron Pacific Indonesia. Jaringan pipa digunakan untuk sarana pengiriman hasil produksi minyak dari stasiun-stasiun pengumpul minyak ke stasiun pengumpul untuk kemudian dijual di titik serah terima di pelabuhan dan kilang minyak milik Pertamina di Dumai, sementara pipa distribusi gas digunakan untuk mendistribusikan gas hasil produksi dan juga yang dibeli dari pihak ketiga, ke stasiun pembangkit listrik dan pembangkit uap.

Integritas pipa penyalur menjadi isu yang mengemuka, selain karena usia pipa-pipa penyalur yang sudah berumur, juga tingkat resiko terhadap keselamatan dan lingkungan semakin meningkat ketika terjadi kebocoran pipa, Usaha pemeliharaan pipa yang dilakukan telah berhasil menahan kenaikan tingkat kegagalan, namun ditengah kondisi penurunan produksi dan harga komoditi minyak, maka diperlukan program dan strategi pemeliharaan pipa yang lebih baik.

Pengembangan program pemeliharaan pipa dan prioritisasinya dilakukan dengan menggunakan metode kajian resiko dan penentuan tingkat resiko yang dapat diterima. Rekomendasi program dan prioritisasi pemeliharaan pipa yang diajukan tetap mempertimbangkan hasil analisa faktor-faktor eksternal dan internal yang terkait langsung dan juga analisa akar permasalahan yang sebelumnya dilakukan.

Rencana implementasi dari prioritasi program ini akan dituangkan dalam program tahunan perusahaan dan disetiap akhir program dilakukan kajian terhadap efektivitasnya dengan menetapkan indikator-indikator leading dan lagging yang akan menjadi target yang harus dicapai.

Deskripsi Alternatif :

Crude and gas pipelines are one of the main supporting facilities for production operation in PT. Chevron Pacific Indonesia. The pipeline is used to delivery crude oil production from gathering stations to storage tank for subsequent loading to Pertamina’s refinery in Dumai, while gas pipelines are used to distribute own gas production and purchased gas from third party, to power and steam generator stations.

The integrity of the pipeline system is become an emerging issue, due to the aging pipelines as well as the increased level of safety and environmental risk when the pipeline leak occurs. Pipeline maintenance had been done and successfully maintained the rate of failure, but with the current situation of production declining and lower price of oil commodity, a better pipeline maintenance program and strategy is needed.

Development of pipeline maintenance program and prioritization is performed by using risk assessment method and risk screening for acceptable level risk. The proposed program and prioritization also consider analysis results of internal and external factors that directly related and root causes of problems.

The implementation plan of maintenance program and prioritization will be set forth in the company’s annual program and to be reviewed in every end of year for the effectiveness by establishing leading and lagging indicator as targets to be achieved.

Copyrights : Copyright (c) 2001 by Perpustakaan Digital ITB. Verbatim copying and distribution of this entire article is permitted by author in any medium, provided this notice is preserved.

Beri Komentar ?#(0) | Bookmark

PropertiNilai Properti
ID PublisherJBPTITBPP
OrganisasiS
Nama KontakUPT Perpustakaan ITB
AlamatJl. Ganesha 10
KotaBandung
DaerahJawa Barat
NegaraIndonesia
Telepon62-22-2509118, 2500089
Fax62-22-2500089
E-mail Administratordigilib@lib.itb.ac.id
E-mail CKOinfo@lib.itb.ac.id

Print ...

Kontributor...

  • Yuliani Dwi Lestari, Ph.D., Editor: Neng Kartika

File PDF...