PERENCANAAN METODA PELAKSANAAN KONSTRUKSI PEKERJAAN STRUKTUR GEDUNG CENTER FOR INFRASTRUCTURE AND BUILT ENVIRONMENT ITB DENGAN MODIFIKASI PADA PELAT LANTAI

CONSTRUCTION METHOD PLANNING OF STRUCTURAL WORKS OF CENTER FOR INFRASTRUCTURE AND BUILT ENVIRONMENT ITB BUILDING WITH MODIFICATION ON THE SLAB

Undergraduate Theses from JBPTITBPP / 2017-04-21 07:38:46
Oleh : GRESNA SEKAR PERTIWI (NIM : 15010089), S1 - Department of Civil Engineering
Dibuat : 2014, dengan 8 file

Keyword : perencanaan metode konstruksi, pekerjaan struktur, pekerjaan beton, pekerjaan beton prategang, pekerjaan baja

Pembangunan gedung Center for Infrastructure and Built Environment (CIBE) ITB merupakan salah satu program pengembangan sarana prasarana yang dilakukan oleh Institut Teknologi Bandung dalam rangka mewujudkan visi menjadi world class university. Pembangunan gedung ini tentunya memerlukan manajemen konstruksi yang baik. Salah satu aspek penting dalam manajemen konstruksi adalah aspek perencanaan pelaksanaan konstruksi pekerjaan struktur.

Dalam proyek pembangunan gedung CIBE ITB, pelaksanaan konstruksi pekerjaan struktur dibagi menjadi dua pekerjaan utama, yaitu pekerjaan beton dan pekerjaan baja. Pekerjaan beton terdiri dari pekerjaan balok, pelat, kolom, retaining wall, lift wall, strong wall and floor dan tangga. Pada pekerjaan beton, pengecoran untuk balok dan pelat dilakukan secara bersamaan dan dibagi menjadi 4 (empat) zona pada tiap lantai gedung. Proses pengecoran pekerjaan struktur yang harus dilakukan secara kontinyu dilakukan dengan menggunakan concrete pump. Sedangkan pekerjaan pengecoran stuktur lainnya dibantu dengan alat concrete bucket. Pekerjaan beton prategang pada struktur strong wall and floor dilakukan dengan metode prategang post-tension, dimana tulangan pada struktur akan diberikan tegangan setelah elemen struktur di cor sebelumnya. Pekerjaan baja terdiri dari pekerjaan struktur atap laboratorium dan canopy. Pekerjaan baja dimulai dari fabrikasi elemen struktur baja di workshop, proses transportasi, serta proses ereksi dan instalasi di lokasi proyek.

Pada perencanaan metode pelaksanaan pekerjaan struktur gedung CIBE ITB ini, ditentukan urutan pekerjaan, langkah-langkah dan ketentuan/peraturan dalam melaksanaan pekerjaan ditambah dengan memperhatikan aspek K3. Selain itu, dianalis juga kebutuhan bahan, pekerja dan alat yang disesuaikan dengan Standar Nasional Indonesia Pekerjaan Beton dan Pekerjaan Baja tahun 2008.

Deskripsi Alternatif :

The construction of the Center for Infrastructure and Built Environment (CIBE) ITB building is one of the infrastructure development program conducted by the Bandung Institute of Technology in order to realize the vision of becoming a world class university. This building would need a good system of construction management. One important aspect of the construction management is construction planning for the structural works.

In the construction project of CIBE ITB building, the structural works is divided into two main works, concrete work and steel work. Concrete work consist of plates works, columns, retaining wall, lift wall, strong wall and floor and also stairs. In concrete work, beams and slab casting process have to be done simultaneously and divided into 4 (four) zones on each floor of the building. Casting process of the works have to be done using concrete pump. Meanwhile, for the other structural works can be assisted with concrete bucket tool. Prestressed concrete work on the structure of the strong wall and floor, done with post-tension prestressing method, in which the structure will be given reinforcement on structural elements after the casting process had done. Steel work consists of laboratory steel roof and canopy. The steel Works begin on the steel fabrication of steel structural elements in the workshop, transport processes, as well as the erection and installation at the project site.

In this construction method planning of structural Works in CIBE ITB building, in this paper determined the sequence of work, measures and provisions/regulations in carrying out the work coupled with consideration of K3. In addition, this paper also analyzed the material requirements, labor and tools based on Standar Nasional Indonesia Pekerjaan Beton dan Pekerjaan Baja year 2008.

Beri Komentar ?#(0) | Bookmark

PropertiNilai Properti
ID PublisherJBPTITBPP
OrganisasiS1 - Department of Civil Engineering
Nama KontakUPT Perpustakaan ITB
AlamatJl. Ganesha 10
KotaBandung
DaerahJawa Barat
NegaraIndonesia
Telepon62-22-2509118, 2500089
Fax62-22-2500089
E-mail Administratordigilib@lib.itb.ac.id
E-mail CKOinfo@lib.itb.ac.id