Path: Top » S1-Final Project » Electrical Engineering » 2007

KAJIAN KEMAMPUAN PERALATAN SISTEM TENAGA DI INDUSTRI SEMEN

Undergraduate Theses from JBPTITBPP / 2009-02-02 15:05:12
Oleh : FARI PRATOMOSIWI (NIM 13203059), S1 - Department of Electrical Engineering
Dibuat : 2007, dengan 7 file

Keyword : CPP, ETAP power station

PT. XYZ, Tbk berencana untuk membangun Captive Power Plant (CPP) di salah satu pabriknya di Narogong Bogor. Sebelum pembangunan CPP dimulai maka diperlukan kajian tentang kondisi kelistrikan eksisting dan rencana kelistrikan sampai sepuluh tahun kedepan. Kajian menitikberatkan pada evaluasi kemampuan peralatan sistim tenaga yang terpasang. Tugas akhir ini mengkaji kemampuan peralatan sistim tenaga di PT. XYZ, Tbk. Analisa yang dilakukan meliputi studi aliran daya dan hubung singkat. Studi aliran daya dilakukan untuk mengevaluasi rating peralatan yang meliputi transformator daya, busbar, circuit breaker dan fuse. Sedangkan studi hubung singkat dilakukan untuk mengevaluasi kapasitas breaking dari circuit breaker dan fuse. Kajian dilakukan dibagi menjadi tiga skenario. Skenario pertama adalah tenaga listrik PT. XYZ disuplay oleh PLN seperti kondisi eksisting saat ini. Skenario kedua adalah tenaga listrik PT. XYZ disuplay oleh CPP saja, sedangkan skenario ketiga adalah PT. XYZ disuplay PLN dan CPP. Hasil kajian akan memberikan skenario kelistrikan yang paling baik dan rekomendasi peralatan tenaga tambahan yang diperlukan agar skenario yang dipilih bekerja dengan baik. Kajian kelistrikan yang dilakukan menggunakan software ETAP Power Station (Electrical Transient Analyzer Program) versi 4.00.

Deskripsi Alternatif :

PT. XYZ , Tbk is going to build Captive Power Plant (CPP) in one of their factory in Narogong Bogor. In order to build the CPP, the power system in PT. XYZ needs to be reviewed in ten years time. This study focused on evaluation of the installed electrical apparatuses capability. This final work reviewed the installed electrical apparatuses capability in PT. XYZ , Tbk. The analysis consists of load flow and short circuit study. Load flow study is carried out to evaluate rating capacity of power transformer, busbar, circuit breaker and fuse. Meanwhile, short circuit study is carried out to evaluate breaking capacity of circuit breaker and fuse. This study is based on three scenarios. In the first scenario, PT. XYZ's power system is supplied only by PLN which is the existing power system. In the second scenario, PT. XYZ's power system is supplied only by CPP and in the third scenario, it is supplied by both PLN and CPP. The final objective of this study is determining the best power system scenario is best to be applied in PT. XYZ and giving recommendation additional electrical apparatuses that's needed to support each scenario. The study has been done using ETAP power system (Electrical Transient Analyzer Program) version 4.00.

Copyrights : Copyright Â(c) 2001 by ITB Central Library. Verbatim copying and distribution of this entire article is permitted by author in any medium, provided this notice is preserved.

Beri Komentar ?#(1) | Bookmark

PropertiNilai Properti
ID PublisherJBPTITBPP
OrganisasiS1 - Department of Electrical Engineering
Nama KontakDrs. Mahmudin, SIP.
AlamatJl. Ganesha 10
KotaBandung
DaerahJawa Barat
NegaraIndonesia
Telepon62-22-2509118, 2500089
Fax62-22-2500089
E-mail Administratordigilib@lib.itb.ac.id
E-mail CKOdigilib@lib.itb.ac.id