PENINGKATAN PRODUKTIVITAS PEKERJAAN BEKISTING KOLOM PREFABRIKASI PADA KONSTRUKSI GEDUNG BERTINGKAT MENGGUNAKAN TIME MOTION STUDIES

Undergraduate Theses from JBPTITBPP / 2017-09-27 10:25:48
Oleh : AHMAD KAMALUR RIDHO (NIM : 15005105); Pembimbing : Ir. Muhamad Abduh, M.T., Ph.D., S1 - Department of Civil Engineering
Dibuat : 2011, dengan 8 file

Keyword : Produktivitas, Bekisting, Kolom, Time Motion Studies, Flow Chart, Process Chart, Crew Balance Chart, Cycle Chart.

Pekerjaan bekisting kolom adalah salah satu bagian penting dari pekerjaan konstruksi pada bangunan. Dan industri konstruksi adalah salah satu industri yang dinamis dan selalu berkembang, khususnya dalam teknologi infrastruktur. Banyak pengembangan metoda pelaksanaan pekerjaan bekisting yang telah dilakukan untuk meningkatkan produktivitas, dan salah satunya adalah bekisting prefabrikasi. Bekisting prefabrikasi telah menjadi komponen struktur sementara yang sangat penting untuk proyek gedung bertingkat. Dan pada akhirnya, tujuan dari penelitian tugas akhir ini adalah untuk meningkatkan produktivitas pekerjaan bekisting kolom prefabrikasi pada konstruksi gedung bertingkat menggunakan metoda time motion studies.Pekerjaan bekisting kolom terbatas pada pekerjaan pemasangan bekisting kolom, dan pengolahan data untuk meningkatkan produktivitasnya menggunakan metoda flow chart, process chart, crew balance chart, dan cycle chart. Metoda time motion studies adalah pengamatan langsung di proyek gedung bertingkat, Apartemen Grand Royal Panghegar, Kota Bandung, Propinsi Jawa Barat, Indonesia. Pengambilan data dilakukan dengan cara merekam dan menggunakan alat perekam seperti handycam atau stopwatch, dan papan tampilan. Hasil dari pengamatan ini adalah dihasilkannya waktu siklus dengan data setiap task, setiap orang yang bekerja, serta posisi dan lokasi sumber daya yang ada di setiap proses pekerjaan.




Metoda flow chart, process chart, crew balance chart, dan cycle chart menggunakan data waktu siklus hasil pengamatan dan membandingkannya dengan waktu siklus usulan dari masing-masing metoda. Waktu siklus usulan dari metoda yang pertama akan digunakan dalam metoda selanjutnya sehingga mendapatkan peningkatan produktivitas yang maksimum pada metoda terakhir. Peningkatan produktivitas tersebut merupakan hasil terbaik untuk usulan pekerjaan bekisting prefabrikasi di lapangan dengan cara merampingkan pekerjaan dari beberapa sisi. Hasil analisis tersebut ditampilkan dalam bentuk tabel, gambar dan grafik. Ada beberapa faktor yang mempengaruhi nilai produktivitas pekerjaan bekisting kolom prefabrikasi. Faktor-faktor tersebut adalah variasi jarak transportasi bekisting, keterbatasan alat, ruang kerja, ruang penyimpanan alat, serta manajemen pekerja dan metoda pelaksanaan proyek secara keseluruhan.

Deskripsi Alternatif :

Column formwork works is one important part of construction work on the building. And construction industry is one industry that is dynamic and always evolving, especially in technology infrastructure. Much development formwork works implementation method that has been done to improve productivity, and one of which is prefabricated formwork. Prefabricated formwork has been a component of a temporary structure that is essential for high rise building projects. And in the end, the purpose of this research is to improve the productivity of the column formwork works in the construction of prefabricated buildings using time-motion method studies.Column formwork works is limited only to the column formwork installation work, and process data using the method of flow charts, process charts, crew balance chart, and the cycle chart. Method of time-motion studies is direct observation at high rise building project, Grand Royal Panghegar Apartments, Bandung, West Java Province, Indonesia. Data is collected by recording and using recording devices such as camcorders or stopwatch, and display boards. The results of these observations is the production cycle time with data every task, every person who works, as well as the position and location of existing resources in each work process. Method of flow charts, process charts, crew balance chart, and the cycle chart using the cycle time data observation and compare it with the proposed cycle time of each method. The cycle time of the first proposal of the method to be used in subsequent method thus getting maximum productivity gains in the last method. Increased productivity is the result of the proposed work best for prefabricated formwork on the ground in a way to streamline the work of several sides. The results are displayed in the form of tables, figures and graphs.




There are several factors that affect productivity value of column prefabricated formwork works. These factors are the variation distance transportation of formwork, the limitations of equipment, work space, storage space tool, as well as labor management and overall project implementation method.

Beri Komentar ?#(0) | Bookmark

PropertiNilai Properti
ID PublisherJBPTITBPP
OrganisasiS
Nama KontakUPT Perpustakaan ITB
AlamatJl. Ganesha 10
KotaBandung
DaerahJawa Barat
NegaraIndonesia
Telepon62-22-2509118, 2500089
Fax62-22-2500089
E-mail Administratordigilib@lib.itb.ac.id
E-mail CKOinfo@lib.itb.ac.id

Print ...

Kontributor...

  • Pembimbing : Ir. Muhamad Abduh, M.T., Ph.D., Editor: Alice Diniarti

File PDF...